On 28.01.2021 17:35, Ian Jackson wrote: > This documents our practice, established in 2018 > https://lists.xen.org/archives/html/xen-devel/2018-07/msg02240.html > et seq > > CC: Jürgen Groß <jgross@suse.com> > CC: Paul Durrant <xadimgnik@gmail.com> > CC: Wei Liu <wl@xen.org> > Signed-off-by: Ian Jackson <iwj@xenproject.org> > --- > docs/process/xen-release-management.pandoc | 12 ++++++++++-- > 1 file changed, 10 insertions(+), 2 deletions(-) > > diff --git a/docs/process/xen-release-management.pandoc b/docs/process/xen-release-management.pandoc > index e1aa1eda8f..a5d70fed67 100644 > --- a/docs/process/xen-release-management.pandoc > +++ b/docs/process/xen-release-management.pandoc > @@ -15,8 +15,10 @@ that they can have an idea what to expect from the Release Manager. > > # Xen release cycle > > -The Xen hypervisor project now releases every 8 months. The actual release date > -depends on a lot of factors. > +The Xen hypervisor project now releases every 8 months. We aim to > +release in the first half of March/July/November. These dates have > +been chosen to avoid major holidays and cultural events; if one > +release slips, ideally the previous release cycle would be shortened. s/previous/subsequent/ ? > @@ -33,6 +35,12 @@ During freeze period, the tree is closed for new features. Only bug fixes are > accepted. This period can be shorter or longer than 2 months. If it ends up > longer than 2 months, it eats into the next development period. > > +The precise release schedule depends on a lot of factors and needs to > +be set afresh by the Release Manager in each release cycle. When the > +release is in March, particular consideration should be given to the > +Chinese New Year holidaty which will then typically occur curing the > +freeze, so the freeze should probably be extended to compensate. s/curing/during/ I suppose, and there's a stray t in "holiday". Lgtm apart from these - feel free to translate to an ack if you think one is needed. Jan
Jan Beulich writes ("Re: [PATCH] xen-release-management doc: More info on schedule"): > On 28.01.2021 17:35, Ian Jackson wrote: > > -The Xen hypervisor project now releases every 8 months. The actual release date > > -depends on a lot of factors. > > +The Xen hypervisor project now releases every 8 months. We aim to > > +release in the first half of March/July/November. These dates have > > +been chosen to avoid major holidays and cultural events; if one > > +release slips, ideally the previous release cycle would be shortened. > > s/previous/subsequent/ ? No, we should go back in time and retrospectively not have slipped after all :-). > Lgtm apart from these - feel free to translate to an ack if you > think one is needed. Thanks for the review. I have put your ack on it indeed and will push it in a moment. Ian.
diff --git a/docs/process/xen-release-management.pandoc b/docs/process/xen-release-management.pandoc index e1aa1eda8f..a5d70fed67 100644 --- a/docs/process/xen-release-management.pandoc +++ b/docs/process/xen-release-management.pandoc @@ -15,8 +15,10 @@ that they can have an idea what to expect from the Release Manager. # Xen release cycle -The Xen hypervisor project now releases every 8 months. The actual release date -depends on a lot of factors. +The Xen hypervisor project now releases every 8 months. We aim to +release in the first half of March/July/November. These dates have +been chosen to avoid major holidays and cultural events; if one +release slips, ideally the previous release cycle would be shortened. We can roughly divide one release into two periods. The development period and the freeze period. The former is 6 months long and the latter is about 2 @@ -33,6 +35,12 @@ During freeze period, the tree is closed for new features. Only bug fixes are accepted. This period can be shorter or longer than 2 months. If it ends up longer than 2 months, it eats into the next development period. +The precise release schedule depends on a lot of factors and needs to +be set afresh by the Release Manager in each release cycle. When the +release is in March, particular consideration should be given to the +Chinese New Year holidaty which will then typically occur curing the +freeze, so the freeze should probably be extended to compensate. + # The different roles in a Xen release ## Release Manager
This documents our practice, established in 2018 https://lists.xen.org/archives/html/xen-devel/2018-07/msg02240.html et seq CC: Jürgen Groß <jgross@suse.com> CC: Paul Durrant <xadimgnik@gmail.com> CC: Wei Liu <wl@xen.org> Signed-off-by: Ian Jackson <iwj@xenproject.org> --- docs/process/xen-release-management.pandoc | 12 ++++++++++-- 1 file changed, 10 insertions(+), 2 deletions(-)